Documents available Friday, February 17, 2023

Bid Document Request Forms may now be emailed to biddoc@bsu.edu

Scope of Work

Removal of Previously-abandoned steam piping and equipment, replacement of air handling unit, reconfiguration of pumps and associated piping.

ESTIMATED COST OF CONSTRUCTION: $565,000.00

ANTICIPATED START DATE:  December 18, 2023
SUBSTANTIAL COMPLETION DATE:  January 19, 2024

Related Documents

Notice to Bidders

Plan Holder List

Addendum No. 1 - 3/1/2023

Addendum No. 2 - 3/7/2023

Documents are available and may be obtained by faxing or emailing the Bid Document Request Form (PDF) to Purchasing Services 765-285-1756 or biddoc@bsu.edu The online documents require Adobe Reader. If you are having trouble viewing documents, try using a different browser, such as Firefox or Chrome.